Rough Order of Magnitude (ROM) estimates are used to support strategic decisions, long-range planning, or to provide a quick sense of project size.
They are often requested to answer high-level questions such as:
- How big is the bread box?
- Roughly speaking, how much are we talking about?
The first step is determining whether a ROM estimate is appropriate. Review the project charter and scope documents to understand what work is required, and conduct a preliminary complexity assessment to help answer the following questions:
- Is the estimate needed to support strategic decisions, long-range planning, or general sizing?
- Would a less precise estimate still be useful for making a decision right now? For example:
- Can we afford something within this cost range?
- Would an estimate with an accuracy range of ±50% be acceptable at this stage?
- Is the estimate needed on short notice (e.g., within a week)?
ROM estimates should not be used when precise figures or a high level of confidence are required. They are typically the first estimate developed for a project and are often used during early discussions or project initiation activities.